The kick-off meeting was organized regarding the development of the Preliminary Design of Podgorica – Bar highway: TOLOŠI – VIRPAZAR section.

The 44 km long section is a joint part of the corridor of the Bar – Boljare highway and the Adriatic – Ionian highway. The project envisages 9 bridges, 10 tunnels, 4 interchanges and several different service facilities which support the operation of the highway.

The meeting was attended by representatives of Monteput as the Investor and representatives of the design teams and partners from Montenegro.

CIPTeam presented the methodology and project implementation schedule and introduced the team of responsible designers by key areas.

At the meeting, the key milestones in the beginning of the development of the Preliminary Design were defined together with planned implementation timelines. Through a pragmatic discussion with a high level of motivation, key challenges were identified together with allocated risks for this initial phase of the design development.